Canaport LNG
Client: LNG Canada
Project Dates: Aug 2009 – Jan 2010
Type of Work: Electrical & Instrumentation Construction
Project Hours: 106,100
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, High Voltage Terminations, Grounding, Fire Alarm, Heat Trace, Pre-Commissioning, Civil, HVAC.
![](https://integralenergy.ca/wp-content/uploads/2023/01/12-Major-Project-Common-Cogeneration-Froth-DSC_0029-EDITED-scaled.jpg)
CNRL Extraction
Client: CNRL
Project Dates: October 2013 – August 2015
Type of Work: Electrical & Instrumentation Construction
Project Hours: 584,792
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, Fibre Optic, High Voltage Terminations, Grounding, Fire Alarm, Heat Trace, Pre-Commissioning, Civil, HVAC.
![](https://integralenergy.ca/wp-content/uploads/2023/03/Husky-Sunrise-CPF-EDITED-1-scaled.jpg)
Husky Sunrise CPF
Client: Husky
Project Dates: June 2012 – Aug 2015
Type of Work: Electrical & Instrumentation Construction
Project Hours: 909,677
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, Fibre Optic, High Voltage Terminations, Grounding, Fire Alarm, Heat Trace, Pre-Commissioning, and Commissioning
![](https://integralenergy.ca/wp-content/uploads/2023/01/Kearl-Lake-Froth-Treatment-2-EDITED.jpg)
Kearl Lake
Client: Krupp Canada
Project Dates: April 2011 – January 2013
Type of Work: Electrical & Instrumentation Construction
Project Hours: 107,823
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, Fibre Optic, High Voltage Terminations, Grounding, Ehouses, Fire Alarm, Heat Trace, Pre-Commissioning.
![](https://integralenergy.ca/wp-content/uploads/2022/11/DJI_0421-EDITED-scaled.jpg)
Keyera Sulphur Plant
Client: Keyera
Project Dates: July 2020 – Ongoing
Type of Work: Electrical & Instrumentation Construction
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, High Voltage Terminations, Grounding, Fire Alarm, Heat Trace, Pre-Commissioning, Temp Power, Care & Preservation, MCC Buildings, Instrumentation
![](https://integralenergy.ca/wp-content/uploads/2022/11/DJI_0015-EDITED.jpg)
LNG Kitimat
Client: LNG Canada
Project Dates: April 2019 – Dec 2021
Type of Work: Electrical & Instrumentation Construction
Project Hours: 100,000
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Conduit, Cable, Lighting and Control, Grounding, Fire Alarm, Heat Trace, Temp Power, Care & Preservation, High Voltage cable installation with Terminations & Testing, Installation of switch gears and transformers.
![](https://integralenergy.ca/wp-content/uploads/2023/01/nwr-sturgeon-constuction-site-con-Copy.jpg)
NWR Refinery
Client: NWR
Project Dates: May 2015 – November 2016
Type of Work: Electrical & Instrumentation Construction
Project Hours: 238,050
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, Fibre Optic, High Voltage Terminations, Grounding, Fire Alarm, Pre-Commissioning, Temp Power, Civil, Care & Preservation, MCC Buildings.
![](https://integralenergy.ca/wp-content/uploads/2023/01/StatOil-EDITED-scaled.jpg)
Statoil Leismer
Client: Statoil Leismer
Project Dates: Apr 2009 – Dec 2015
Type of Work: Electrical & Instrumentation Construction
Project Hours: 36,020
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, Fibre Optic, High Voltage Terminations, Grounding, Fire Alarm, Heat Trace, Pre-Commissioning.
![](https://integralenergy.ca/wp-content/uploads/2022/12/KBR-Suncor-Fort-Hills-Secondary-Extraction-EDITED.jpg)
Suncor Forthills Secondary
Client: Suncor
Project Dates: Oct 2015 – Dec 2017
Type of Work: Electrical & Instrumentation Construction
Project Hours: 978,517
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, Fibre Optic, High Voltage Terminations, Grounding, Fire Alarm, Heat Trace, Telecom, Temp Power, MCC Buildings.
- Installation of 1,500 linear meters of DarmaTech Insulation