Projects

Industrial - LNG & Pipelines

Non-Process Buildings

Client: LNG Canada
Project Dates: Aug 2020 – Oct 2022
Type of Work: Electrical Construction of 15 Non Process Buildings and shelters
Project Hours: 59,000
  • Project Management; Project Planning, Procurement, Quality & Safety.
  • Installation of Temp Power, Electrical Service, Lighting, Lighting Control, Grounding, Fire Alarm, Power Distribution of 8kv, 600v 120/208 systems, Fiber Optics

LNG Kitimat

Client: LNG Canada
Project Dates: April 2019 – Dec 2021
Type of Work: Electrical & Instrumentation Construction
Project Hours: 100,000
  • Project Management; Project Planning, Procurement, Quality & Safety.
  • Installation of Conduit, Cable, Lighting and Control, Grounding, Fire Alarm, Heat Trace, Temp Power, Care & Preservation, High Voltage cable installation with Terminations & Testing, Installation of switch gears and transformers.

LNG Canada River Water Intake

Client: LNG Canada
Project Dates: Apr 2021 – Oct 2021
Type of Work: Electrical Construction of power and fiber system for River Water Intake
Project Hours: 10,300
  • Project Management; Project Planning, Procurement, Quality & Safety.
  • Installation of 6.9Kv Power Feeds with termination and splicing Installation of backbone fiber system with testing

CNRL Infrastructure, Logistic, & Project Control Work 2020

Client: CNRL
Project Dates: Jan 2020 – Dec 2020
Type of Work: Electrical & Instrumentation Construction
Project Hours: 19,000
  • Project Management; Project Planning, Procurement, Quality & Safety.
  • Installation of Cable Tray, Cable, Lighting, High Voltage Terminations, Grounding, Fire Alarm, Heat Trace, Pre-Commissioning, Temp Power, Civil, HVAC, Care & Preservation, MCC Buildings.

CNRL Infrastructure, Logistic, & Project Control Work 2019

Client: CNRL
Project Dates: Jan 2019 – Dec 2019
Type of Work: Electrical & Instrumentation Construction
Project Hours: 19,000
  • Project Management; Project Planning, Procurement, Quality & Safety.
  • Installation of Cable Tray, Cable, Lighting, High Voltage Terminations, Grounding, Fire Alarm, Heat Trace, Pre-Commissioning, Temp Power, Civil, HVAC, Care & Preservation, MCC Buildings.

Glenboro and Saint Leon Line 3

Client: Enbridge
Project Dates: July 2018 – April 2019
Type of Work: Electrical & Instrumentation Construction
Project Hours: 22,176
  • Project Management; Project Planning, Procurement, Quality & Safety.
  • Installation of Cable Tray, Cable, Lighting, Grounding, Fire Alarm, Heat Trace, Temp Power, Instrumentation, Cathodic Protection, HVAC, Care & Preservation, MCC Buildings.