View our Current and Past Projects LNG & Pipelines LNG Canada NON-PROCESS BUILDINGSAug 2020 – Oct 2022 Hours-59,000
Electrical Construction of 15 Non Process Buildings and shelters:
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Temp Power, Electrical Service, Lighting, Lighting Control, Grounding, Fire Alarm, Power Distribution of 8kv, 600v 120/208 systems, Fiber Optics.
LNG Canada Cedar Valley LodgeApril 2019 – Dec 2021 Hours-100,000
Electrical & Instrumentation Construction:
- Project Management; Project Planning, Procurement, Quality & Safety.
Installation of Conduit, Cable, Lighting and Control, Grounding, Fire Alarm, Heat Trace, Temp Power, Care & Preservation, High Voltage cable installation with Terminations & Testing, Installation of switch gears and transformers.
LNG Canada River Water IntakeApr 2021 – Oct 2021 Hours-10,300
Electrical Construction of power and fiber system for River Water Intake
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of 6.9Kv Power Feeds with termination and splicing Installation of backbone fiber system with testing
CNRL Infrastructure, Logistic, & Project Control Work 2020Jan 2020 – Dec 2020 Hours-19,000
Electrical & Instrumentation Construction:
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, High Voltage Terminations, Grounding, Fire Alarm, Heat Trace, Pre-Commissioning, Temp Power, Civil, HVAC, Care & Preservation, MCC Buildings.
CNRL Infrastructure, Logistic, & Project Control Work 2019Jan 2019 – Dec 2019 Hours-19,000
Electrical & Instrumentation Construction:
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, High Voltage Terminations, Grounding, Fire Alarm, Heat Trace, Pre-Commissioning, Temp Power, Civil, HVAC, Care & Preservation, MCC Buildings.
Enbridge – Glenboro and Saint Leon Line 3 July 2018 – April 2019 Hours-22,176
Electrical & Instrumentation Construction:
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, Grounding, Fire Alarm, Heat Trace, Temp Power, Instrumentation, Cathodic Protection, HVAC, Care & Preservation, MCC Buildings.
Enbridge – Langbank Line 3 June 2018 – Feb 2019 Hours-5,979
Electrical & Instrumentation Construction:
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, Grounding, Fire Alarm, Heat Trace, Temp Power, Instrumentation, Cathodic Protection, HVAC, Care & Preservation, MCC Buildings.
Burstall Ethane Storage Production Phase Oct 2017 – Nov 2018 Hours-15,650
Electrical & Instrumentation Construction:
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, High Voltage Terminations, Grounding, Fire Alarm, Instrumentation, Heat Trace, Pre-Commissioning, Temp Power, Fibre Optic, Care & Preservation, MCC Buildings.
Burstall Ethane Storage Wash Phase Aug 2016 – March 2017 Hours-8,800
Electrical & Instrumentation Construction:
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, Fibre Optic, High Voltage Terminations, Grounding, Fire Alarm, Instrumentation, Heat Trace, Pre-Commissioning, Temp Power, Care & Preservation, MCC Buildings.
Enbridge Athabasca Terminal – Late Works Project Apr 2013 – Feb 2014 Hours-39,500
Electrical & Instrumentation Construction:
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, Fibre Optic, High Voltage Terminations, Grounding, Fire Alarm, Heat Trace, Pre-Commissioning.
Enbridge Athabasca Terminal – Upgrade ProjectMay 2012 – Feb 2013 Hours-34,000
Electrical & Instrumentation Construction:
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, Fibre Optic, High Voltage Terminations, Substation installation, Grounding, Heat Trace, Insulation, Pre-Commissioning assistance.
Alliance Pipeline Ltd. - Jetpac Control System UpgradeMar 2012 – Sept 2012 Hours-34,000
Electrical & Instrumentation Construction:
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, Fibre Optic, High Voltage Terminations, Grounding, Fire Alarm, Heat Trace, Pre-Commissioning, Temp Power, Civil, HVAC, Care & Preservation, MCC Buildings.
Canaport LNG Tank 3Aug 2009 – Jan 2010 Hours-106,100
Electrical & Instrumentation Construction:
- Project Management; Project Planning, Procurement, Quality & Safety.
- Installation of Cable Tray, Cable, Lighting, High Voltage Terminations, Grounding, Fire Alarm, Heat Trace, Pre-Commissioning, Civil, HVAC.
|